FPSO Loop & Termination Diagrams

Project Description

Bluewater's Instrument and Electrical division engaged Solutions Technology's draughting office to draught 1,340 electrical loop and termination diagrams from paper copies of marked up Bluewater drawings.

This work was completed in a 14 week period which included the 3 week Christmas break. The draughting office management systems ensured that all the drawings were registered, revised, checked and issued in accordance with Bluewater's project procedures and engineering standards.

Solutions Technology draughting office completed the project within the very tight contractual schedule. After the official handover, Bluewater's Instrument & Control Engineer Mr Paul Sep stated that he "would like to use the final progress graph for presentation purposes to indicate that sometimes projects do go as scheduled."

Browse our project gallery by selecting the image below.
(View at 1024x768xTrue Colour)


Graph showing project progress